
PAGE 4

THE CONSTRUCTION OF BILBERRY RESERVOIR
Bilberry Reservoir was constructed in the year
1840, at the head of a narrow gorge or glen, leading from
Holmebridge to the high bluff of land called Good Bent,
and is supplied by two streams flowing through the cloughs,
running to the north east and south east of Good Bent, and
draining the moors of Holme Moss on the one side, and the
hills running up to Saddleworth on the other, including
some thousands of acres of moorland.
The extent of the surface drained is estimated
at 14,000 acres, which, reckoning at 2 inches of rain in
twenty-four hours, would give 101,640,000 cubic feet of
water.
The confluence of the two streams takes place
between two large hills, called Hoobroom Hill and Lumb Bank,
and which run parallel with each other for a distance of
about 150 yards, when they open out, and form an extensive
oval basin of not less than three hundred yards in diameter.
The reservoir was formed by blocking up the
valley below this basin, so as to enclose some fifteen or
twenty acres of surface. Situated as it is, at the top
of a narrow gauge or glen, it presented engineering difficulties
of no common character.
These difficulties were taken into consideration
to begin with, and Mr. George Leather, C.E., was engaged
to prepare the plans and specifications.
The construction of the reservoir was let to
Messrs. Sharp and Sons, of Dewsbury, for £9,324 and the
construction was proceeded with under this contract.
The embankment was so formed that it was presumed
it would constitute a barrier secure enough against any
accumulation of water the heaviest rains could supply.
The embankment was about three hundred feet across, and
about sixty seven feet high, and was formed of earth, stones,
etc., such as the district supplied, with a wall of what
is called “puddle” through its centre, sixteen feet thick
at the bottom, and eight feet thick at the top. This puddle
was composed of clay, gravel, etc., and the object of introducing
it was to render the embankment water tight, and so prevent
leakage of the water.
The bye-wash, or waste-pit, which was a circular
chimney about five yards in diameter, was on the south or
the right hand side of the reservoir, and was sunk through
the embankment near to its junction with Hoobroom Hill,
and communication with a tunnel, emptying itself on the
lower or outer side of the embankment. Its height from
the bed of the reservoir was fifty-nine feet.
The outlet of water was by an open culvert.,
along the bed of the reservoir, communicating with the tunnel
referred to by two patent trap-doors, or shuttles, situated
directly parallel to each other at the bottom of the chimney,
and were worked by perpendicular rods raised by a common
screw on a platform at the top of the chimney. In the event
of the trap door being insufficient to carry the surplus
water away during extraordinary supplies, the water, on
rising to the level of the chimney or bye-wash, would meet
with a source of escape presumed to be adequate to all contingencies.
At a subsequent period the embankment considerably
settled in one or two places near the centre, and its surface
was thus lowered below the level of the bye-wash, which
was thereby rendered useless for the taking away of surplus
or flood water.
Whilst the embankment was being constructed, a dispute arose
with Messrs. Sharp and Sons, and the contract with them
was broken. Messrs. David Peter and Brothers undertook
in 1848 to complete the work.
It was stated at the time that in blasting the
rock for the purpose of getting a firm foundation for the
puddle-wall, the workmen struck into a spring about the
thickness of a man’s arm, and instead of this being carried
off so as not to interfere with the work, an attempt was
made to carry it up the embankment, and force it into the
inside.
This injured the puddle by keeping it too soft,
and it appears to have been the first great error in the
construction of the embankment. Mr Leather, the engineer,
however, on the other hand, declared an oath before the
coroner’s jury that he never heard of the spring; but the
workmen declared that they waited five or six weeks for
him to come and look at it, and that this delay cost the
contractors £200 or £300.
When Messrs.
Potter took the work in hand, they opened the
embankment, and put in a great amount of material, with
the view of preventing a rupture. When the work had been
going on for some time, they informed the Commissioner that
they had got low enough, and that a further opening would
have to be made, and more puddle put in if the evil was
to be remedied.
But the commissioners declined to go to further
expense, as the construction of Homestyes and Boshaw Whams
reservoirs, and sundry law expenses, had been so heavy.
Thus the embankment from the first was leaky,
and these leaks increasing in number and power, caused the
embankment to sink below the water pipe. Sometimes these
leaks were so serious that they would supply the mills without
his having to attend to the shuttles.
In February, 1852, one of these shuttles was
under repair, and the workman had suspended the work until
he could learn who was to pay him his wages; and the other
shuttle was so blocked up with stones, ling, &c., that
very little water would escape. This was the condition
of the shuttles on the night of the 4th of February,
1852.
